Planned water main works on Old Bedstone Road, Redlake Place and a section of the B4367

28th March 2022

Planned water main works commencing 27 June 2022, working under four phases to approximately 31 August 2022.

The below four phases are currently being finalised and a programme of works are in production, upon completion of this programme more information will become available.

Phase 1 will be under a road closure ( Old Bedstone Road)

Phase 2 will be signs and barriers with a one-way closure ( Redlake Place)

Phase 3 will be under three-way traffic lights (B4367 on the bridge)

Phase 4 will be under two-way traffic lights ( close to the entrance to Old Bedstone Road from the B4367)

Last modified: 28th March 2022